CEYPORT Taşucu Handles 91-Meter Wind Turbine Blades in Major Port Operation
Noted by Michael Jones · 385 reads
CEYPORT Taşucu unloaded 42 blades measuring 91 meters each and 70 turbine tower sections, using its port and back-area capacity for project cargo.

CEYPORT Taşucu International Port in Mersin has handled 42 wind turbine blades, each 91 meters long, along with 70 tower sections. The operation tested the port’s ability to move oversized project cargo from vessel to storage and onward through its logistics area, while managing the demands of cargo that cannot be handled like standard freight.
The blades exceed the 90.26-meter blade handled at a Turkish port the previous year, according to the account of the operation. Together with the tower pieces, the shipment represents more than 1,200 tons of wind turbine components brought to the port for renewable energy projects. The cargo was discharged and transferred to a waiting area; the port says the work was completed without errors.
Space and vessel access for project cargo
For cargo of this size, berth access is only one part of the operating challenge. A port needs room to position equipment, control turning movements, move loads safely between vessel and shore, and hold components without obstructing other activity. CEYPORT Taşucu says its layout and available storage space allowed it to handle the blade transfer while keeping port traffic moving.
The facility has 380,000 square meters of marine area and reports a total capacity of 1.5 million square meters across its port, logistics and industrial areas. The breakdown given is 500,000 square meters for the port area, 330,000 square meters for the designated logistics area and 714,000 square meters for the designated industrial area. These areas give the operator room to stage large components and coordinate cargo movements beyond the quay.
Its 1.3-kilometer dock has 10 berths for different vessel types and a current depth of 12 meters. The port says that depth is expected to reach 14 meters after dredging. The change could expand vessel access for heavy-tonnage ships carrying large project loads, although the account does not give a completion date for the work.
Equipment and handling sequence
CEYPORT Taşucu attributes the operation to its infrastructure, mobile cranes and experienced teams. The cranes are electrified and have high lifting capacities, while the handling plan relies on engineering calculations and coordinated work during discharge and transfer. With a 91-meter blade, positioning and clearance become central parts of the job: each move has to account for the component’s length and the available operating space.
The port’s stated cargo capabilities span containers, bulk cargo, general cargo, project cargo and roll-on/roll-off freight. That mix matters operationally because specialized cargo movements take place within a working port that also serves other vessel and cargo needs. The operator says its area and maneuvering capacity let it stage the turbine components without disrupting regular traffic.
The shipment included two sets of 42 blades and 70 wind turbine towers, according to the account, and totalled more than 1,200 tons. The reported figure covers the turbine components brought to the port; no per-piece weights, vessel details or onward transport routes were provided. Those details would help carriers and project teams assess the equipment and road or sea movements needed after the port transfer.
Port’s role in renewable energy logistics
CEYPORT Taşucu is a subsidiary of CEY Holding. The company has invested in the port’s dock, infrastructure, superstructure, industrial facilities and technology, and describes the site as a base for special project transport as well as general cargo. Its location in Mersin places the facility in the Eastern Mediterranean, where the port is seeking a larger role in moving equipment for renewable energy projects.
CEY Holding Chairman Ali Avcı said the operation depended on engineering, technical infrastructure and back-area capacity. He described the discharge of the 91-meter blades as evidence of the port’s ability to coordinate specialized cargo work and said the company intends to build its position as a Mediterranean logistics base.
For project cargo planners, the practical measure is whether a port can receive oversized components, move them through the terminal and stage them for the next leg without creating bottlenecks. CEYPORT Taşucu’s operation demonstrates that it handled blades of this length alongside tower sections at scale. Berth depth, yard capacity, crane capability and the coordination of vessel-to-yard transfers will remain the details to track as the port pursues additional renewable energy cargo.